    Capacity Upgrade Skids for Santos

    IMG_0254

    IMG_0254

    IMG_0380

    IMG_0380

    IMG_0049 - Copy

    IMG_0049 - Copy

    1/7

    Supply eight (8) sets of Capacity Upgrade skids and piping for Santos Ltd.

    Two off dual Separator packages.

    Four off triple Separator packages.

    Two off quad Separator packages.

    October 2014.

    Value: $3,300,000.00

     

    The following scope of work was carried out:

    • Procure all piping, bolts, gaskets and structural materials.

    • Fabrication of skid frames, piping and Separator vessels.

    • Non-destructive testing of piping and Separator vessels.

    • Hydrostatic testing of piping and Separator vessels.

    • Surface treatment of all skid frames, piping and vessels to Santos specifications.

    • Complete assembly of skid packages.

    • Dispatch skid packages.