Fabricate & assembly of fuel gas skids
First fabricated in 2018, IIM has completed the same skids over several years (up to 2026)
Value: $3,000,000+ depending on quantity of skids fabricated
The following scope of work was carried out:
-
Originally all materials were free issued, but recent projects IIM have procured all pipe & fittings including studs, gaskets, valves, regulators, drainers, flexible hoses, evaporation tanks, filters & SS tube
-
Latest projects include heat tracing & insulation
-
100% Visual Inspection of all welds
-
5% NDT
-
Hydrotesting
-
Painting of piping spools (2 -coat system)
-
Assembly including N2 testing & flange management sheets
-
Packaging of completed skids onto pallets for Transport to site
-
QA and MDR as applicable (ITP, WPS, Material certs and MDR)